The Public Works Authority (Ashghal) has announced the completion of the first package of the Roads and Infrastructure Development Project in Al Ebb and Leabaib and the completion of the fifth package of the project.

Eng. Abdulla Al Naemi, Head of the Northern Areas Section of the Roads Projects Department at Ashghal, said Ashghal is implementing a plan to provide integrated infrastructure services and facilities and advanced road networks in the areas of Al Ebb and Leabaib.

The plan includes five packages that will serve a total of 5,592 residential plots when completed.

Package 1 as well as the main works of package 5 have been completed, and works for packages 2, 3, and 4 are currently underway.

He said packages 1 and 5 serve a total of 1,910 residential plots for citizens’ subdivisions, and have achieved significant improvements in the area by providing advanced infrastructure services and an internal roads network. Ashghal has completed all the main works of package 5 of the project, and work is currently under way to complete house connections and beautification works. (QNA)page 16