AIMING to provide advanced roads that provide easy access to the 2022 World Cup stadiums, the Public Works Authority 'Ashghal' has started working on a new project to upgrade link roads to Al-Bayt Stadium in Al Khor.
The project features the construction of 5.3 kilometres of roads, with three lanes in each direction, all leading to four sides of the stadium. These roads will facilitate access to bus stations and car parking around the stadium, and will also provide multiple entrances to the Sports Complex where the stadium is located.
These roads will also provide two links to the south and east of Al Khor Expressway, which is currently under construction, and a link to Al-Egda Street, which is located to the north of the stadium.
The new roads will feature an 8.55m-wide pedestrian path and cycle path, in addition to landscaping and pavement works that will be carried out on the surrounding roads.
Besides, a 7.3 km section of Al Egda Street will be upgraded to include three lanes in each direction, with a 3m-wide pedestrian path provided on each side of the street, starting from the roundabout at the entrance of Al Khor City until reaching the northwest side of Al-Bayt Stadium. It will also be connected to Al Khor Expressway, which is considered the main road leading to the stadium.
Eight signal-controlled intersections will be constructed as part of the project, in addition to four signal-controlled intersections on the Al-Khor Expressway. Two junctions will also be provided only for traffic heading to and from the roads surrounding the stadium. Speed humps will be provided in order to reduce speed at these intersections to maintain the safety of road users.
Additionally, the project includes the construction of a 2.2 km long gravity sewer network, a separate surface water drainage network and an irrigation network bringing treated wastewater to and around the stadium from the TSE network located near Al Khor Corniche.
Intelligent telecommunications systems (ITS) will be installed in this project, and street lighting will be provided using energy saving LED street lights.
The project is located in the south of Al Khor. Barriers, warning lights and road signs were installed around the construction site to warn off local residents. A community outreach officer was appointed at the project site to inform residents about the project and coordinate with other service authorities like Al Khor Municipality and other relevant entities.
Safety instructions in 'Ashghal Road Safety Handbook' and other applicable quality standards are strictly followed on all construction sites. Furthermore, all guidelines related to the preservation of environment as well as workplace safety standards and regulations for workers, visitors and local residents are fully implemented.
Bin Omran Trading & Contracting Company started the project last September. Most of the major works are scheduled to be completed by the end of Q2, 2018, whereas the project works will be finally completed in Q1, 2019 at a total cost of QR 354,181,808.30.