Continued from page 1 ?
The second part of the project includes a pumping station with 10 pumps and auxiliary facilities. The pumping station will be located at the end of Mesaimeer Tunnel south of Hamad International Airport.
The pumping station will operate at a capacity of 19.7 cubic metres per second and its function is to pump water from Mesaimeer Tunnel, which was completed in 2016, to the new outfall tunnel.
The project is designed to ensure the preservation of the marine environment, as the water that will be pumped complies with the environmental assessment standards, and it is discharged 10 kilometres off-shore to reduce the effect on the marine environment.